Dundon-Berchtold Hall Construction Begins

February 2, 2018

Construction on Dundon-Berchtold Hall will begin on Monday, February 5, according to Jim Ravelli, university operations. This will be the first construction of a new building in the middle of campus since Franz Hall was built in 1995 and, as with any major building project in such a central location, there will be some impacts that can be minimized, but not entirely avoided. Beginning Monday, employees will begin to see an increase in activity on and around the site as contractors begin to mobilize. The main concern is the safety of everyone on campus, so please stay alert to contractor vehicles and trucks as they come and go, and be aware of these additional impacts the project will make:

Expanded fencing: One of the first activities will be the expansion of fencing around the site. Fencing will be expanded outward to include half the main road across from the Pilot House and towards Waldschmidt Hall. This will eliminate the sidewalk that extends from Shipstad to the roadway by Romanaggi Hall. The sidewalk next to Waldschmidt that runs in front of Christie will remain open for pedestrians. There will also be temporary walkways on the Shipstad side of the sequoias from Christie to the main drive.

Parking impact: Unfortunately, there is no way to avoid the loss of several parking spots as the fencing expands into the roadway along the main entrance drive. This will affect all of the parking along the construction side of the main drive from the turnaround by the Pilot House to Waldschmidt. Parking on the side of the drive adjacent to Buckley and Romanaggi will remain available.

Traffic access: Because the fence will extend into the street, the road will be limited to a one-way only lane between the turnaround by the Pilot House and the Waldschmidt parking lot.  Traffic from the Waldschmidt lot area will be required to leave campus via the Kenna Hall exit.  As construction begins, a flagger will be on site to assist drivers who are headed past the Pilot House towards Waldschmidt Hall.

“Thank you for your patience as we start on this major construction,” says Ravelli. “I know it will require some adjustment for everyone, but the end reward of a new academic hall will be worth the temporary impact. Please plan on seeing regular construction updates from me as the project progresses.”

For more information contact Ravelli at 7540 or go to www.up.edu/uo.

Share this post:

Share on X (Twitter) Share on Facebook Share on LinkedIn Share on Email Share on WhatsApp

Filed Under: 02-05-2018, Campus Services, University Operations Tagged With: Dundon-Berchtold Hall, Jim Ravelli, University Operations

Primary Sidebar

Submit a Feature to UPBeat

Want to share your announcement in the PilotsUP Digest? Follow the link below to submit your request.

Submit an Announcement to PilotsUP

UpDate

Susan Mcdaniel and Nicole Hanig, Music, will be performing on the concert series “Chatter PDX” on June 1 at 10:30 a.m. at the Pacific Center with Hilary Oseas, viola and James Shields, clarinet, both of the Oregon Symphony. There will also be spoken word from former professional football player and writer, Marcus Lattimore, in the hour-long concert. Tickets and information at ChatterPDX.

Maureen Briare, Nursing & Health Innovations, published Fountain of Life Mass Setting, with a special dedication to the priests and brothers of the Congregation of Holy Cross at the University of Portland. GIA Publications. Released April, 2025 

Mohammadhadi Hajilou, Engineering, presented “Effect of fuel size, ignition energy, and wind speed on smoldering to flaming transition of Douglas fir lumber.” Co-presenters: R. Spring, N. Bolden, A. Henry, T. Rowley, A. Burton. 14th US Combustion Meeting, Boston, MA. March 16-19, 2025. Hajilou also published “Fire Whirl Emissions and Burning Rates for Crude Oil Slicks of Varying Thickness.” Co-authors: J. Dowling, W. Cui, M. Gollner. Fuel, 393 138482 (2025).

Kiya Riverman, Environmental Science, was awarded a grant for $489,935.00 on behalf of the U.S. Department of Defense, for her research “Impacts of spatial-temporal precipitation, snowpack properties, and snowmelt variability on alpine landscapes and runoff.” February 15, 2025.

Christina Astorga, Theology, served as a Member of the Editorial Board for the Journal of Moral Theology. February 26 – July 7, 2019. Astorga also served as the Head of the Local Arrangement Committee for the Catholic Theological Society of America. June 13, 2024 – June 15, 2025

Mohammad Arbabian, Business, published “Optimal Inventory Management Policies When Supply Is Bundled.” 9th North American Conference on Industrial Engineering and Operations Management, Washington D.C. June, 2024. Arbabian also published “Evaluating the Role of 3D Printing in Decentralized Supply Chains: A Stackelberg Framework for Optimal Manufacturing Decisions.” 15th International Conference on Industrial Engineering and Operations Management. February, 2025.

Aziz Inan, Engineering, has been credited for his research on palindrome dates in multiple news outlets including: USA Today, NDTV, NBC New York, News9live, Courier Journal, 13newsnow.com, Ozarksfirst.com, Inquirer.net, Austin American-Statesman, and The News of Israel.

Update Archive

About

UPBeat is a newsletter for University of Portland faculty and staff published through the Division of Enrollment Management, Marketing, & Web Services. Submit your listing information our online form. Submission deadline is noon the Thursday prior to publication. Submissions may be edited for clarity, consistency, brevity, or style.

August 2025
M T W T F S S
 123
45678910
11121314151617
18192021222324
25262728293031
« May    
  • Email
  • Facebook
  • Instagram
  • RSS
  • YouTube

Copyright © 2025 · University of Portland